Line Item Number Description Units Quantity
2021.501/00010 MOBILIZATION LS 1
2101.524 CLEARING AND GRUBBING TREE 13
2104.502/00130 REMOVE PIPE APRON EACH 9
2104.502/00780 REMOVE MANHOLE EACH 1
2104.503/00285 REMOVE SEWER PIPE (STORM) L F 86
2104.503/00290 REMOVE SEWER PIPE (SANITARY) L F 184
2104.504/00050 REMOVE CONCRETE WALK S Y 55
2104.504/00130 REMOVE BITUMINOUS SURFACING S Y 750
2105.601/00015 DEWATERING LS 1
2105.604 45 MIL EPDM LINER S Y 120
2106.607 COMMON EMBANKMENT (CV) (P) CU YD 2,320
2106.607 COMMON EXCAVATION (P) CU YD 6,975
2211.607 AGGREGATE BASE (CV) CLASS 5 CU YD 81
2411.507/04050 GRANULAR BACKFILL (CV) C Y 14
2501.502 54" RC PIPE APRON W/ TRASH GUARD EACH 1
2501.502 73" SPAN RC PIPE-ARCH APRON W/ TRASH GUARD EACH 2
2501.503/19732 73" SPAN RC PIPE-ARCH CULV CL IIA L F 53
2501.503/24543 54" RC PIPE CULVERT DES 3006 CL III L F 4
2503.602 54" RC BEND - 22.5 EACH 1
2503.602/00320 CONNECT TO EXISTING STORM SEWER EACH 1
2504.602 12" PVC CAP EACH 2
2511.504/00014 GEOTEXTILE FILTER TYPE 4 S Y 75
2511.507/00014 RANDOM RIPRAP CLASS III C Y 34
2511.609 QUARTZITE ROCK TON 102
2521.618 5" CONCRETE WALK S F 4,930
2574.507/00104 BOULEVARD TOPSOIL BORROW C Y 296
2575.523/00020 RAPID STABILIZATION METHOD 3 MGAL 6.6
2575.601/00030 EROSION CONTROL LS 1
2575.605/00070 TURF ESTABLISHMENT ACRE 1.1