Line |
Item Number |
Description |
Units |
Quantity |
ADD-01 |
126 |
2545.502 |
LIGHTING UNIT TYPE E (festoon light and cable) |
L F |
500 |
ADD-02 |
127 |
2104.504 |
REMOVE BITUMINOUS DRIVEWAY PAVEMENT |
S Y |
521 |
ADD-03 |
127 |
2104.518 |
REMOVE CONCRETE WALK |
S F |
31,851 |
ADDISON LOT |
128 |
2104.502 |
REMOVE BOLLARD |
EACH |
20 |
128 |
2104.502 |
REMOVE LIGHT FOUNDATION |
EACH |
1 |
129 |
2104.503 |
SAWING CONCRETE PAVEMENT (FULL DEPTH) |
LIN FT |
392 |
130 |
2104.504 |
REMOVE CONCRETE PAVEMENT |
SQ YD |
2,818 |
131 |
2104.601 |
SALVAGE SIGNS |
LUMP SUM |
1 |
132 |
2106.507 |
EXCAVATION - COMMON |
CU YD |
281 |
133 |
2106.507 |
EXCAVATION - SUBGRADE |
CU YD |
55 |
134 |
2211.507 |
AGGREGATE BASE (CV) CLASS 5 |
CU YD |
464 |
135 |
2301.504 |
CONCRETE PAVEMENT 6.0" |
SQ YD |
2,654 |
136 |
2503.503 |
15" RC PIPE SEWER DESIGN 3006 CLASS V |
LIN FT |
110 |
137 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN H |
LIN FT |
3.5 |
138 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020 |
LIN FT |
3.9 |
139 |
2521.518 |
6" CONCRETE WALK |
SQ FT |
535 |
140 |
2531.503 |
CONCRETE CURB AND GUTTER DESIGN B412 |
LIN FT |
63 |
141 |
2531.503 |
CONCRETE CURB AND GUTTER DESIGN B612 |
LIN FT |
129 |
142 |
2582.503 |
4" SOLID LINE PAINT WHITE |
LIN FT |
2,405 |
143 |
2582.518 |
PAVEMENT MESSAGE PAINT |
SQ FT |
13.2 |
base |
37 |
2502.503 |
8" TP PIPE DRAIN |
LF |
213 |
ELEC |
90 |
2545.501 |
LIGHTING SYSTEM WIRE & CONNECTIONS - (3rd Street Circuitry Main to Lyon St) |
LUMP SUM |
1 |
91 |
2545.502 |
LIGHT UNIT TYPE A FOOTING (Lyon & 3rd Street North of Lyon St.) |
EACH |
32 |
92 |
2545.502 |
LIGHT UNIT TYPE B FOOTING + POLE INSTALLATION (3rd Street between Main & Lyon) |
EACH |
9 |
101 |
2545.503 |
1" RIGID NON-METALLIC CONDUIT - SCH 40 |
LIN FT |
1,200 |
102 |
2545.503 |
2" RIGID NON-METALLIC CONDUIT - SCH 40 |
LIN FT |
1,580 |
103 |
2550.602 |
SERVICE CABINET + DMX CONTROL CABINET |
LUMP SUM |
1 |
MMU |
4 |
2104.502 |
REMOVE GATE VALVE |
EACH |
3 |
5 |
2104.502 |
REMOVE HYDRANT |
EACH |
1 |
12 |
2104.502 |
SALVAGE GATE VALVE & BOX |
EACH |
1 |
51 |
2504.601 |
TEMPORARY WATER SERVICE |
LUMP SUM |
1 |
52 |
2504.602 |
CONNECT TO EXISTING WATER MAIN |
EACH |
4 |
53 |
2504.602 |
HYDRANT |
EACH |
2 |
54 |
2504.602 |
1" CORPORATION STOP & SADDLE |
EACH |
24 |
55 |
2504.602 |
6" GATE VALVE AND BOX |
EACH |
3 |
56 |
2504.602 |
8" GATE VALVE AND BOX |
EACH |
6 |
57 |
2504.602 |
1" CURB STOP |
EACH |
24 |
58 |
2504.603 |
1" TYPE PE PIPE |
LIN FT |
984 |
59 |
2504.603 |
4" PVC WATERMAIN |
LIN FT |
11 |
60 |
2504.603 |
6" PVC WATERMAIN |
LIN FT |
62 |
61 |
2504.603 |
8" PVC WATERMAIN |
LIN FT |
1,496 |
62 |
2504.604 |
4" INSULATION |
SQ YD |
50 |
63 |
2504.608 |
WATERMAIN FITTINGS |
POUND |
826 |
SWM |
6 |
2104.502 |
REMOVE DRAINAGE STRUCTURE |
EACH |
16 |
13 |
2104.503 |
REMOVE SEWER PIPE (STORM) |
LIN FT |
558 |
40 |
2503.503 |
15" RC PIPE SEWER DESIGN 3006 CLASS V |
LIN FT |
1,345 |
41 |
2503.503 |
18" RC PIPE SEWER DESIGN 3006 CLASS III |
LIN FT |
207 |
42 |
2503.503 |
24" RC PIPE SEWER DESIGN 3006 CLASS III |
LIN FT |
221 |
43 |
2503.503 |
30" RC PIPE SEWER DESIGN 3006 CLASS III |
LIN FT |
341 |
45 |
2503.602 |
CONNECT TO EXISTING STORM SEWER |
EACH |
3 |
65 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN H |
LIN FT |
10.5 |
66 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020 |
LIN FT |
79.6 |
67 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN 60-4020 |
LIN FT |
19 |
68 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN 72-4020 |
LIN FT |
17.3 |
69 |
2506.503 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 1 |
LIN FT |
68.2 |
72 |
2506.602 |
SAFLE BAFFLE W/BRACING KIT |
EACH |
1 |
Uncategorized |
1 |
2011.501 |
MOBILIZATION |
LUMP SUM |
1 |
2 |
2101.502 |
CLEARING |
EACH |
17 |
3 |
2101.502 |
GRUBBING |
EACH |
17 |
7 |
2104.502 |
REMOVE LIGHT FOUNDATION |
EACH |
40 |
8 |
2104.502 |
REMOVE PLANTER |
EACH |
8 |
9 |
2104.503 |
SAWING CONCRETE PAVEMENT (FULL DEPTH) |
LIN FT |
113 |
10 |
2104.503 |
SAWING BITUMINOUS PAVEMENT (FULL DEPTH) |
LIN FT |
419 |
11 |
2104.502 |
SALVAGE CASTING |
EACH |
1 |
14 |
2104.503 |
REMOVE CURB AND GUTTER |
LIN FT |
3,770 |
15 |
2104.603 |
REMOVE & ABATE ASBESTOS-CONTAINING PIPES |
LIN FT |
250 |
16 |
2104.504 |
REMOVE PAVEMENT |
SQ YD |
10,978 |
17 |
2104.601 |
SALVAGE SIGNS |
LUMP SUM |
1 |
18 |
2104.602 |
SALVAGE MANHOLE & CASTING |
EACH |
1 |
19 |
2104.502 |
REMOVE STEAM VAULT |
EACH |
1 |
20 |
2105.607 |
STRUCTURAL SOIL BORROW (CV) |
CU YD |
120 |
21 |
2106.507 |
EXCAVATION - COMMON (P) |
CU YD |
5,840 |
22 |
2106.507 |
EXCAVATION - SUBGRADE |
CU YD |
1,200 |
23 |
2106.507 |
SELECT GRANULAR EMBANKMENT (CV) (P) |
CU YD |
3,717 |
24 |
2106.507 |
COMMON EMBANKMENT (CV) (P) |
CU YD |
161 |
25 |
2106.607 |
EXCAVATION - SPECIAL |
CU YD |
400 |
26 |
2106.607 |
HAUL AND DISPOSE OF CONTAMINATED MATERIAL |
CU YD |
400 |
27 |
2108.504 |
GEOTEXTILE FABRIC TYPE 7 |
SQ YD |
9,429 |
28 |
2123.51 |
COMMON LABORERS |
HOURS |
20 |
29 |
2123.51 |
3.0 CU YD SHOVEL |
HOURS |
20 |
30 |
2123.61 |
SKID LOADER |
HOURS |
20 |
31 |
2211.507 |
AGGREGATE BASE (CV) CLASS 5 (P) |
CU YD |
2,730 |
32 |
2301.502 |
DOWEL BAR |
EACH |
1,548 |
33 |
2301.602 |
DRILL & GROUT REINFORCEMENT BAR (EPOXY COATED) |
EACH |
184 |
34 |
2301.603 |
PERMANENT HEADER |
LIN FT |
245 |
35 |
2301.504 |
CONCRETE PAVEMENT 7.0" |
SQ YD |
8,980 |
36 |
2360.509 |
TYPE SP 9.5 WEARING COURSE MIXTURE (3,C) |
TON |
108 |
38 |
2502.503 |
4" PERF TP PIPE DRAIN |
LIN FT |
3,007 |
39 |
2502.603 |
INSTALL 6" TP PIPE DRAIN |
LIN FT |
1,000 |
46 |
2503.602 |
8"X4" PVC WYE |
EACH |
1 |
47 |
2503.602 |
8"x6" PVC WYE |
EACH |
21 |
49 |
2503.603 |
4" PVC SANITARY SERVICE PIPE |
LIN FT |
8 |
50 |
2503.603 |
6" PVC SANITARY SERVICE PIPE |
LIN FT |
898 |
64 |
2506.502 |
INSTALL CASTING |
EACH |
1 |
71 |
2506.602 |
ADJUST FRAME AND RING CASTING (SPECIAL) |
EACH |
2 |
73 |
2506.602 |
CONNECT TO EXISTING DRAINAGE STRUCTURE |
EACH |
2 |
74 |
2506.602 |
CASTING ASSEMBLY SPECIAL |
EACH |
17 |
75 |
2521.518 |
4" CONCRETE WALK |
SQ FT |
2,333 |
76 |
2521.518 |
6" CONCRETE WALK |
SQ FT |
34,830 |
77 |
2521.618 |
6" CONCRETE WALK SPECIAL |
SQ FT |
7,675 |
78 |
2521.618 |
SPECIAL SURFACE TREATMENT |
SQ FT |
1,675 |
79 |
2531.503 |
CONCRETE CURB AND GUTTER DESIGN B418 |
LIN FT |
1,009 |
80 |
2531.503 |
CONCRETE CURB AND GUTTER DESIGN B618 |
LIN FT |
2,853 |
81 |
2531.503 |
CONCRETE CURB AND GUTTER DESIGN D418 |
LIN FT |
145 |
82 |
2531.504 |
7" CONCRETE DRIVEWAY PAVEMENT |
SQ YD |
620 |
83 |
2531.618 |
TRUNCATED DOMES |
SQ FT |
319 |
84 |
2540.602 |
GATEWAY MONUMENT COLUMN AND FOOTING |
EACH |
2 |
85 |
2540.603 |
DECORATIVE STONE BLOCK |
EACH |
7 |
86 |
2540.602 |
BENCH TYPE 1 |
EACH |
6 |
87 |
2540.602 |
TRASH RECEPTACLE |
EACH |
4 |
88 |
2540.602 |
RECYCLE RECEPTACLE |
EACH |
4 |
89 |
2540.602 |
BIKE RACK |
EACH |
5 |
93 |
2545.502 |
LIGHT UNIT TYPE C (Light Bollard) |
EACH |
9 |
94 |
2545.502 |
LIGHT UNIT TYPE D (Monument Accent Light) |
EACH |
2 |
95 |
2545.602 |
GFCI DUPLEX PEDESTAL (On Footing) |
EACH |
12 |
96 |
2545.602 |
20 AMP - EVENT POWER PEDESTAL (On Footing) |
EACH |
1 |
97 |
2545.602 |
50 AMP - EVENT POWER PEDESTAL |
EACH |
3 |
98 |
2545.602 |
BOLLARD - SALVAGE & REINSTALL |
EACH |
10 |
99 |
2545.602 |
BOLLARD - NEW |
EACH |
12 |
100 |
2545.602 |
INGRADE HANDHOLE |
EACH |
4 |
104 |
2563.601 |
TRAFFIC CONTROL |
LUMP SUM |
1 |
105 |
2563.601 |
ALTERNATE PEDESTRIAN ROUTE |
LUMP SUM |
1 |
106 |
2564.601 |
INSTALL SIGN |
LUMP SUM |
1 |
107 |
2565.616 |
REVISE SIGNAL SYSTEM |
SYSTEM |
1 |
108 |
2571.524 |
DECIDUOUS TREE 2.5" CAL B&B |
EACH |
32 |
109 |
2571.525 |
DECIDUOUS SHRUB NO 5 CONT |
EACH |
82 |
110 |
2571.527 |
PERENNIAL NO 1 CONT |
EACH |
550 |
111 |
2571.527 |
PERENNIAL BULBS |
EACH |
420 |
112 |
2571.602 |
TREE GRATE WITH FRAME |
EACH |
12 |
113 |
2573.501 |
STORM DRAIN INLET PROTECTION |
LUMP SUM |
1 |
114 |
2573.501 |
STABILIZED CONSTRUCTION EXIT |
LUMP SUM |
1 |
115 |
2574.507 |
COMMON TOPSOIL BORROW (Seed) |
CU YD |
130 |
116 |
2574.508 |
FERTILIZER TYPE 3 |
POUND |
60 |
117 |
2574.507 |
BOULEVARD TOPSOIL BORROW (Plantings) |
CU YD |
215 |
118 |
2575.505 |
SEEDING |
ACRES |
0.2 |
119 |
2575.508 |
MNDOT SEED MIX 25-131 |
POUND |
44 |
120 |
2575.508 |
HYDRAULIC MULCH MATERIAL |
POUND |
600 |
121 |
2575.509 |
RAPID STABILIZATION METHOD 3 |
M GALLON |
6 |
122 |
2582.503 |
4" SOLID LINE PAINT WHITE |
LIN FT |
2,716 |
123 |
2582.503 |
4" BROKEN LINE MULTI-COMPONENT GROUND IN (WR) CONTRAST |
LIN FT |
600 |
124 |
2582.518 |
PAVEMENT MESSAGE PAINT |
SQ FT |
17.6 |
125 |
2582.503 |
24" SOLID LINE PREFORM THERMO GROUND IN ENHANCED SKID RESISTANCE |
LIN FT |
130 |
125 |
2582.518 |
CROSS WALK PREFORM THERMO GROUND IN CONTRAST ENHANCED SKID RESISTANCE |
SQ FT |
954 |
WW |
44 |
2503.602 |
CONNECT TO EXISTING SANITARY SEWER |
EACH |
2 |
48 |
2503.603 |
8" PVC PIPE SEWER |
LIN FT |
1,342 |
70 |
2506.603 |
CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 2 |
LIN FT |
44 |