Line |
Item Number |
Description |
Units |
Quantity |
Base Bid |
1 |
1050.000/00000 |
BASE BID |
L S |
1 |
2 |
1110.000/00000 |
REPLACE DETERIORATED ROOF SHEATHING |
S F |
1 |
3 |
1120.000/00000 |
REPAIR DETERIORATED RAFTER TAILS |
S F |
1 |
4 |
1130.000/00000 |
WINDOW RESTORATION SINGLE LITE TOWER WINDOW |
EACH |
1 |
5 |
1140.000/00000 |
WINDOW REPLACEMENT SINGLE LITE TOWER WINDOW |
EACH |
1 |
6 |
1150.000/00000 |
WINDOW RESTORATION TANK ROOM WINDOW |
EACH |
1 |
7 |
1160.000/00000 |
WINDOW REPLACEMENT - TOOL ROOM WINDOWS |
EACH |
1 |
8 |
1170.000/00000 |
EXTERIOR DOOR RESTORATION |
EACH |
1 |
9 |
1180.000/00000 |
EXTERIOR DOOR REPLACEMENT |
EACH |
1 |
10 |
1190.000/00000 |
WOOD RESTORATION |
S F |
1 |
11 |
1200.000/00000 |
WOOD REPLACEMENT |
B F |
1 |
12 |
1210.000/00000 |
REPOINT EXTERIOR LIMESTONE WALLS |
L F |
1 |
13 |
1220.000/00000 |
REPLACE DETERIORATED LIMESTONE |
S F |
1 |
14 |
1230.000/00000 |
REPOINT INTERIOR LIMESTONE WALLS |
L F |
1 |
15 |
1240.000/00000 |
RESTORE INTERIOR PLASTER |
S F |
1 |
16 |
1250.000/00000 |
RESTORE INTERIOR DOORS |
EACH |
1 |
17 |
1260.000/00000 |
RESTORE EXTERIOR STUCCO |
S F |
1 |
Alternate 1 |
18 |
1300.000/00000 |
LIGHTNING PROTECTION. |
L S |
1 |
Alternate 2 |
19 |
1310.000/00000 |
CONSTRUCT NEW PINNACLE AND SPIRE |
L S |
1 |
Alternate 3 |
20 |
1320.000/00000 |
STABILIZE THE SOUTH SLOPE |
L S |
1 |
Alternate 4 |
21 |
1330.000/00000 |
REPLACE EXTERIOR CONCRETE STAIRS |
L S |
1 |
Alternate 5 |
22 |
1340.000/00000 |
REPLACE EXTERIOR CONCRETE LANDING/STOOPS |
L S |
1 |
Alternate 6 |
23 |
1350.000/00000 |
STABILIZE WEST SLOPE WITH TERRACING |
L S |
1 |
Alternate 7 |
24 |
1360.000/00000 |
REPLACE ELECTRICAL SYSTEM |
L S |
1 |