Project Items
Line | Item Number | Description | Units | Quantity |
---|---|---|---|---|
Beaver Dam Removal/Culvert Cleaning | ||||
11 | 0 | Beaver Dam Removal/Culvert Cleaning Per Hour |
Per hour | 100 |
Bituminous Road Repair (Pothole Patching) | ||||
5 | 0 | Bituminous Road Repair (Pothole Patching) Ton |
Ton | 150 |
Bituminous Road Repair (Pothole Patching) Hot or Cold mix specified by County | ||||
4 | 0 | Bituminous Road Repair (Pothole Patching) Hot or Cold mix specified by County Per Hour |
Per hour | 400 |
Extra Equipment | ||||
12 | 12 | Wheel Type Front End Load 1 CYD or Greater w/ Operator Per Hour |
Per hour | 1 |
13 | 13 | Excavator w/Operator Per Hour |
Per hour | 1 |
14 | 14 | Skid Steer w/ Operator | Per hour | 1 |
Grading of FAD Roads | ||||
1 | 0 | Grading of FAD Roads Per Hour |
Per hour | 300 |
Gravel Hauling & Application | ||||
2 | 0 | Gravel Hauling & Application Ton |
Ton | 3,000 |
Roadside Mowing & Weed Control | ||||
9 | 0 | Roadside Mowing & Weed Control Per Hour |
Per hour | 550 |
Shoulder Repair (Spot Repairs) | ||||
3 | 0 | Shoulder Repair (Spot Repairs) Ton |
Ton | 1,500 |
Snowplowing Operations | ||||
6 | 0 | Snowplowing Operations Per Hour |
Per hour | 1,800 |
7 | 0 | Snowplowing Operations Ton |
Ton | 1,800 |
Sweeping of FAD Roads | ||||
10 | 0 | Sweeping of FAD roads Per Hour |
Per hour | 150 |
Tree & Brush Cutting | ||||
8 | 1 | Tree & Brush Cutting Per Hour |
Per hour | 450 |