Project Items
Line | Item Number | Description | Units | Quantity |
---|---|---|---|---|
CP 18-200-115 - CR 124 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 260 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CR 170 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 190 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 2 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 454 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 23 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 739 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 25 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 232 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 45 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 106 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 48 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 264 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - CSAH 59 | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 61 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 | |
CP 18-200-115 - Oak Lawn | ||||
2021.501/00010 | MOBILIZATION | LUMP SUM | 1 | |
2331.619/00030 | SEAL BITUMINOUS PAVEMENT CRACKS | ROAD STA | 191 | |
2563.601/00010 | TRAFFIC CONTROL | LUMP SUM | 1 |